US Nuclear Energy Foundation
“Evangelizing Nuclear Advocacy by Bringing Science to Citizens”
A Non-Profit 501(C)(3) Nevada Foundation
PO Box 2867, Sparks, NV 89432 (775) 224-2089
www.usnuclearenergy.org / Email:
comments@usnuclearenergy.org
New Plants
All
information and research on this website is gathered and
used with written
permission
from
the
participating authors, contributors & advisors concerning
nuclear science, energy and waste repository data! US
Nuclear Energy Foundation
is an
independent foundation and not supported exclusively by any industry or
nuclear association but by individual and/or business support in order to retain our
independence of educational materials.
Our mission is to influence change in public
opinion towards
knowledgeable citizens about nuclear energy and waste repository
issues.
“Our freedoms can
only
be maintained by the advancement of technologies that serve mankind—
not
advancing technology puts Freedom at Risk and
our freedom is
threatened because we
don't take the time to
participate in it” GJD
New Nuclear Plant Status
Company
Site, (Plant Site)
Design
# of Units
Early Site Permit (ESP)
Construction / Operating License Submittal
Alternate Energy Holdings / Unistar
Elmore County, ID
EPR
1
-
FY 2009
Amarillo Power / Unistar
Vicinity of Amarillo, TX
EPR
1
-
FY 2009
AmerenUE / Unistar
Callaway County, MO (Callaway)
EPR
1
-
July 2008
Constellation / UniStar
Calvert County, MD (Calvert Cliffs)
EPR
1
-
March 2008
Constellation / UniStar
Oswego County, NY (Nine Mile Point)
EPR
1
-
FY 2009
Detroit Edison
Fermi, MI (Fermi)
ESBWR
1
Not yet determined
FY 2008
Dominion
Louisa County, VA (North Anna)
ESBWR
1
Approved November 2007
November 2007
Duke
Cherokee County, SC (William States Lee)
AP1000
2
-
December 2007
Duke
Davie County, NC
NYD*
-
Under consideration
Not yet determined
Duke
Oconee County, SC (Oconee)
NYD*
-
Under consideration
Not yet determined
Entergy
West Felciana Parish, LA (River Bend)
ESBWR
1
-
FY 2008
Entergy (NuStart )
Claiborne County, MS (Grand Gulf)
ESBWR
1
Approved April 2007
February 2008
Exelon
Clinton, IL (Clinton)
NYD*
-
Approved March 2007
Not yet determined
Exelon
Victoria County, TX
ESBWR
2
-
September 2008
Florida Power & Light
Miami-Dade County, FL (Turkey Point)
AP1000
2
Not yet determined
FY 2009
Luminant
Glen Rose, TX (Comanche Peak)
APWR
2
-
FY 2008
NRG Energy / STPNOC
Matagorda County, TX (South Texas Project)
ABWR
2
-
September 2007
PPL Corp. / Unistar
Luzerne County, PA (Susquehanna)
EPR
1
-
FY 2009
Progress Energy
Wake County, NC (Harris)
AP1000
2
-
February 2008
Progress Energy
Levy County, FL
AP1000
2
-
July 2008
South Carolina Electric & Gas
Fairfield County, SC (V.C. Summer)
AP1000
2
-
March 2008
Southern Company
Burke County, GA (Vogtle)
AP1000
2
Under review, Approval expected early 2009
March 2008
TVA (NuStart )
Jackson County, AL (Bellefonte)
AP1000
2
-
October 2007
30
Bechtel contracted to complete
Watts Bar 2
16 October 2007
Tennessee Valley Authority (TVA) has selected Bechtel to
lead engineering, procurement and construction work to
complete the second unit at the Watts Bar nuclear power
plant.
Watts Bar (Image:
TVA)
Bechtel's contract, valued in reports at $1 billion, is
included in the scope of the five-year $2.49 billion
project to finish the incomplete pressurized water
reactor (PWR), as approved by TVA in August 2007. When
completed in 2012, 40 years after construction first
began, the pressurized water reactor (PWR) will add
about 1200 MWe to TVA's capacity. "We are honoured to be
selected by TVA for this historic assignment," said Jim
Rheinsch, president of Bechtel's nuclear power business.
Work on Watts Bar 2 was suspended in 1985 when the plant
was about 60% complete, but construction can resume
under an existing permit that is valid until 2010.
According to TVA president and CEO Tom Kilgore, Bechtel
will be responsible for completing the engineering
design, procuring equipment and materials and finishing
the physical construction of Watts Bar 2, with oversight
from TVA. "TVA's oversight of Bechtel will include
incorporating the lessons learned from the restart of
Unit 1 at our Browns Ferry Nuclear Plant in Alabama," he
added.
Bechtel was involved in the May 2007 restart of TVA's
Browns Ferry unit 1, providing engineering, start-up and
other technical services in the $1.8 billion project to
restart the mothballed reactor. It also worked on the
restart of Browns Ferry units 2 and 3 in the 1990s and
has carried out steam generator replacements at TVA's
Sequoyah plant as well as Watts Bar 1.
The other bidder for the Watts Bar 2 project was Shaw
Stone and Webster. TVA said it chose Bechtel because of
its "technical capability, overall value and pricing,
quality of proposed project team and other key
attributes."
Bechtel's proposal also includes Washington Group
International and Sargent & Lundy as contractors,
according to Watts Bar 2 Vice President Masoud Bajestani.
Cited in press reports, Bajestani added that TVA was
working to finalize additional contracts with Siemens
for the replacement of major components of the turbine
system and with Westinghouse, the original supplier of
the two Watts Bar PWRs.
TVA's Bellefonte site has been earmarked for the
construction of two new Westinghouse AP1000 reactors by
the NuStart consortium, of which TVA is a member, but
completing Watts Bar 2 will be the fastest and cheapest
way for TVA to bring new capacity on line.
Further information
Bechtel
Tennessee Valley Authority (TVA)